Project: Installing a Black Exposed Fastener Metal Roof
0:00:17 Project Start: The video begins at the "modest house" where the team is installing a black, exposed fastener metal roof, chosen for its cost-effectiveness and low maintenance.
0:00:34 Choice of exposed fastener: The presenter stated that the type of roof is the most cost effective and also low maintenance.
0:00:50 Punching the Roof: They are punching the roof (making pilot holes for screws) because it's a sheathed roof, and the sheets are manageable in size. They also aim to hit the purlins, marking their locations mathematically.
0:01:39 Punching the Roof, atypical method: Punching the roof is not something they would normally do, they would do it for porch roofs.
0:02:49 Layout Considerations: Key layout considerations include:
0:03:23 Visual Representation: A drawing is used to illustrate the roof structure, highlighting the ridge, porch, and the resulting valley. Layout challenges are explained, emphasizing the need to align ribs/flats at key points (valley, corner trim, and porch peak).
0:04:55 Prioritization: The most crucial aspect is ensuring the end of the roof allows for proper corner trim installation. Water management and flashing are prioritized over perfect visual alignment.
0:09:35 Plan of Action: They decide to start at the end and work towards the valley, lapping ribs to ensure water flows over, not into, the joints.
0:10:07 Vapor Dry Underlayment: Vapor Dry underlayment is used, and they discuss how any moisture will be handled by taping and venting.
0:12:34 First Piece Installation: The first piece of metal is positioned, ensuring the rib is correctly placed for the corner trim.
0:13:29 Punch Holes: They note the clean look of a punched and screwed metal roof.
0:13:50 No Foam Closures at Eave: They intentionally omit foam closures at the eave to allow for ventilation and condensation management, relying on the Vapor Dry underlayment.
0:16:12 Acknowledging complaints: The presenter jokes about complaints.
0:16:25 Child: The presenter jokes about not complaining because of his newborn child.
0:17:17 Valley Preparation: Measurements and cuts are made for the valley section.
0:19:13 Installation of Valley Pan: The pan needs to be shingled to fit under the adjacent main roof panel, it goes before the main panel.
0:23:25 Counter Flashing: Counter flashing and taping are used at the transition between the main roof and the valley.
0:23:54 Valley Installation: The W-shaped valley pan is installed, using scrap pieces as guides for a straight line. Sealant is applied under the overlaps.
0:28:59 Closure Foam: They realize they forgot closure foam for the ribbed metal in the valley, delaying the installation of the adjacent steel. They tape off the area due to an upcoming rain event.
0:31:39 Vapor Dry Adhesion: They note that the Vapor Dry adhered well despite challenging installation conditions (low temperature and high winds).
0:32:16 Valley Angle Calculation: They use a large triangle method to accurately determine the valley angle, ensuring straight cuts.
0:34:07 Overlap and Aesthetics: It is mentioned that overlapping pieces causes an unaesthetic look.
0:34:29 Closure under Rib: A closure will be placed under the rib, to avoid ice dam from going up.
0:35:44 Squaring the New Side: They double-check the layout on a new side, adjusting slightly to ensure the rib placement is correct for the gable trim.
0:39:56 Missed Screws: They humorously realize they forgot to install some screws.
0:40:10 Vapor Dry Installation Issues: They discuss issues with the Vapor Dry bubbling due to installation conditions and weather, but confirm it's still adhering.
0:42:11 End-of-Building Check: They carefully measure and adjust as they approach the end of the building, ensuring proper rib alignment.
0:46:39 Porch Delay: They are still awaiting the delivery of the posts.
0:46:54 Porch Material: The porch design requires a 16-foot 6x6 cedar piece, which is proving difficult to source.
0:47:19 Front Section Installation: They proceed with installing metal across the front, skipping the porch area, and continuing into the valley.
0:53:41 Origami folds: They fold the panels to close it with the physical flashings.
0:58:26 Ridge Cap Strategy: They plan to use sealant and a separate piece of flashing under the ridge cap for added water protection, preferring this method over tucking the ridge cap under the steel.
1:05:49 Closure Foam Installation: They install foam closure strips along the valley, explaining their purpose in sealing gaps and preventing water intrusion.
1:16:03 Watertight Status: They confirm the roof is watertight on one side.
1:16:21 Wind Challenges: High winds force them to adjust their plans, focusing on prep work (layout and angle calculations) instead of installing large panels.
1:19:25 Exposed Fastener Concerns: They discuss the inherent risks of exposed fastener roofs, emphasizing the importance of the Vapor Dry and filler strip for protection.
1:31:31 Counter Flashing: They install counter flashing in the valley area.
1:37:58 Valley Completion: They successfully install the valley sections.
1:40:33 Project Summary: They summarize the work completed, noting that only the ridge caps and the porch area remain. It took three days with bad weather to complete.
1:41:29 Tier: The presenter discussed that exposed fastener roofing is just below standing seam, and above asphalt.
1:41:55 Feedback Request: Viewers are encouraged to leave comments about the valley installation and any suggestions.